How to record a scope change before it becomes a dispute

During a planned visit, additional work is suggested. Later, the owner and provider remember different instructions about what was approved.

A useful distinction

A change needs a clear record of the proposed work, its implications and the authorized decision.

The person coordinating access may not have authority to approve additional spending or altered work. Establish that distinction before the visit. Providers should know whom to contact and how a decision will be recorded. Emergency situations require the applicable emergency process; a routine change form must not delay appropriate emergency assistance.

For ordinary changes, describe what prompted the proposal and what remains uncertain. Ask whether the original work can proceed independently and whether the new scope affects other commitments. Qualified advice may be needed to understand technical implications. Avoid authorizing an unclear proposal simply because someone is already on site.

After a decision, update the work record and inform affected people. If the change is declined or deferred, record that too. The final invoice and completion report should be checked against the scope actually approved. This gives the owner a traceable account of the decision rather than a reconstruction based on memory.

Put it into practice

  1. Record the proposed change separately from the original scope.
  2. Request its cost, timing and relevant limitations in writing.
  3. Obtain approval from the authorized decision-maker before treating routine additional work as instructed.

What to verify

Keep the original scope, change request and approval together. A discussion or forwarded quotation should not be represented as approval without supporting evidence.

Your next step

Add a change-approval field to the next planned work record.